Power Supply Improves as TCN Restores Shiroro–Mando Line

Daniel Adaji
Power supply to parts of Kaduna has improved following the restoration of the 330kV Shiroro–Mando Transmission Line 1 by the Transmission Company of Nigeria (TCN).
TCN announced on Monday that the transmission line was successfully restored and is now fully operational after the completion of repair works by its engineers.
According to the company, the line was restored at approximately 3:27pm on Saturday, 14 February 2026.
“The Transmission Company of Nigeria (TCN) has successfully restored the 330kV Shiroro–Mando Transmission Line 1, which is currently operational,” the statement said.
TCN explained that with the restoration of Line 1, “bulk power supply to Kaduna Electric has significantly improved, and power supply constraints previously experienced in Kaduna have been alliviated.”
The company noted that the repair works were carried out by its engineers, leading to the successful energisation of the line and improved electricity delivery to consumers served by Kaduna Electric.
Meanwhile, TCN disclosed that efforts are ongoing to restore the second transmission line on the route.
“Repair works are ongoing on the 330kV Shiroro–Mando Transmission Line 2, and barring any unforeseen circumstances, restoration of Line 2 will be completed soon,” the company stated.
It added that the completion of the second line will “further strengthen network redundancy and the overall system reliability.”
TCN appreciated customers and stakeholders for their patience during the outage period.
“TCN appreciates the patience, understanding, and cooperation of its customers and stakeholders throughout this period and remains firmly committed to delivering stable and efficient transmission service nationwide,” the statement added.
The restoration of the critical transmission infrastructure is expected to enhance grid stability and support improved electricity supply across Kaduna and surrounding areas.